Estimate whole good packages/units per year from an ideal/nameplate rate, hours per shift, whole shifts per operating day, whole operating days per year, and a user-supplied OEE fraction. This is a schedule-based planning estimate, not a forecast, machine guarantee, or standards-compliance result. Inputs must share the same product/package scope and OEE time basis.

Example values are prefilled to demonstrate the calculation. Replace them with values for your product, package, equipment, and operating conditions.

Inputs

Machine and operating schedule

Range: at least 0 units/min

Enter the theoretical package/unit rate before availability, speed, and quality losses. This is not a saleable-good rate. Use the same package/product definition as annual demand. No industry cap is implied; the prefilled rate is illustrative only.

Range: at least 0 hours/shift

Enter planned production hours per shift, excluding breaks and other time outside planned production. Zero hours is valid and returns zero annual output. OEE must use the same planned-time definition.

Range: at least 0 count/day

Enter a whole-number count of shifts per operating day (zero or more). The prefilled shift count is only an example; use the site's actual schedule; zero shifts returns zero annual output.

Range: at least 0 count/year

Enter the site's planned production days in the year, excluding non-operating days. Use a whole number zero or greater; 250 days is an example only, not a standard operating calendar. Zero days returns zero annual output.

Range: 0–1 0–1

Enter a user-measured or approved OEE fraction from 0 to 1 (80% = 0.80), for the same line, product, and planned production time. The prefilled OEE is an example only, not a benchmark.

Result

Estimated annual good-package capacity
19,200,000 units/year
Scheduled production hours per year
4,000.0 h/year
OEE-adjusted good-output rate
80.00 units/min
Theoretical packages before OEE losses
24,000,000.0 units/year
Valid
Capacity estimate scope
Schedule-based estimate only. OEE must match this line, product/package scope, and planned-production-time definition. OEE is applied once to theoretical units, and the annual good-unit result is floored to a whole count. Exclude days and hours not scheduled for production; a zero schedule returns zero annual output.

Calculation

Scheduled production hours per year
—
Theoretical packages before OEE losses
—
OEE-adjusted good-output rate
—
Estimated annual good-package capacity
—